6. What is the Schedule for Replacement Terminal Environmental Assessment Process?

Beginning in September 2018, the Replacement Terminal EA started to gather data, develop sections of the EA, and have held a public scoping meeting on October 23, 2018 and a public meeting on January 23, 2019. The tentative remaining schedule for the TTN Terminal EA is:

  • Continued development of the Draft EA Purpose and Need, Alternatives Analysis, Affected Environment, and Environmental Consequences Sections of the EA

  • Public Meeting 2 – Winter 2019/2020 (December 2019 or January 2020 and one meeting each to be held in Bucks County, PA and Ewing, NJ)

  • Draft Final EA Report Issued/Start of Public Comment Period – Winter 2020 (Minimum Review of 30 days)

  • EA Public Hearing – Winter 2019/2020 (January/February 2020 and 30 days after Draft Final EA Report Issued)

  • Incorporation of Comments and Final EA Submission to FAA – February/March 2020

  • Anticipated FAA Decision – Mid 2020

 

Note that dates are approximate and may change due to data collection, FAA review times, and responding to public questions and comments.